MIDVAAL - The Midvaal Local Municipality this week gave feedback on the progress made with the electrification of Sicelo. The MMC for Engineering, Cllr Reginald Hubbard, held a public meeting with the community of ward 8 on Monday regarding the electrification of the Sicelo community. Midvaal said the project aims to provide electricity to 1200 households and to free the area form illegal connections. According to the municipality, the first phase was completed in 2023 when 200 households received electricity. The second phase aims to electrify 400 households in a period of 6 months.